The 1983 Flood at Glen Canyon
by Steven Hannon
Powell reservoir first filled in June 1980, seventeen
years after the diversion tunnels around the new dam near the lower end
of Glen Canyon were closed. Brim full, the reservoir holds almost
exactly two average annual flows of the Colorado River: twenty-seven
million acre feet (An acre foot will cover one acre with one foot of
water. A football field, minus the end zones, is about an acre). During
the fill period most of the water had to be bypassed to meet downstream
users needs, human as well as wildlife.
Glen Canyon Dam and its reservoir are managed to
maximize electrical power production—a "cash register" that was intended
not only to pay its own construction cost but also the costs of other
Bureau of Reclamation structures in the Colorado River Basin.
Accordingly, once the reservoir topped off, the Bureau has consistently
interpreted the Congressional authorization for the "Glen Canyon Unit"
as requiring Powell to be kept as full as Nature will permit. Under the
government’s ideal scenario, in a non-drought situation, every year the
spring runoff will just, exactly, fill the tank again. The snowpack in
the mountains ringing the Colorado River Upper Basin is monitored and
educated guesses are made about late spring precipitation events.
In early May 1983 the Bureau found itself with too much water in Powell
Reservoir. Winter had lingered unusually long and cold in much of the
high country, and the government’s runoff modeling was, to be kind,
inaccurate. Then it suddenly turned warm and rain began to fall over
much of the 108,000 square mile basin above the reservoir. For the first
time other than for brief tests, the dam’s spillways had to be placed in
service.
Many dams have simple over-the-crest spillways, but large dams,
particularly ones with their powerplants located at the toe of the dam,
must route overflows around the structures. The Bureau’s first big dam,
Hoover, built in the 1930s, uses tunnels. Glen Canyon Dam was designed
in much the same way, incorporating portions of the river diversion
tunnels that had to be constructed around the dam site to manage the
river during construction. It was an efficient arrangement, therefore
appealing to the engineers, because the diversion tunnels could be
partially utilized for the lower ends of the spillways. The downside,
however, is that tunnels have a finite capacity. Boring two or three
thousand feet of tunnel through rock is time consuming and expensive, so
the tunnels were sized in a tradeoff between anticipated flood flows and
cost.
The tunnel spillways at both Hoover and Glen Canyon are not designed to
run full, for then they would be under pressure, like water pipes. In
fact, the tunnels are intended to operate like covered flumes, with a
minimum 30% air gap, at atmospheric pressure, throughout their lengths.
The design capacity of the combined spillways at Glen Canyon is 276,000
cubic feet per second when the reservoir is full. Historic flows in the
Colorado at Lees Ferry (fifteen miles downstream from the dam) have
often exceeded 200,000 cfs, and there is strong evidence, from debris
found at the time Hoover was surveyed, that flows through the Grand
Canyon have exceeded 400,000 cfs.
When the Upper Basin decided to relieve itself purposefully in late May
1983, the Bureau began to bypass a few thousand cfs. To do so, the
spillways’ radial gates were raised, permitting the water to flow under
their lower edges and down the tunnels. Each tunnel carried the water
down at a 55 degree slope through a smooth curve into a horizontal
section that was part of the original river diversion tunnel in both
abutments. Each diversion tunnel was plugged at the point where the
descending spillway curves into the horizontal section. (Behind each
plug is the water pressure at the bottom of the reservoir: 250 pounds
per square inch with a full reservoir.) At the end of each tunnel, the
120-mph jet of water was directed away from the canyon wall and
deflected upward by a 40 degree ramp to dissipate much of the water’s
energy before it hit the river.

June 10, 1965. Bureau of Reclamation visits Cathedral in the Desert
just as reservoir begins to enter. Photograph by Mel Davis, courtesy US
Department of Interior, Bureau of Reclamation.
The spillways had only operated for a few days when a
slight rumbling and vibration began to be felt in the abutments and the
dam itself. Close inspection of the jets emerging from the tunnel
portals revealed some debris being ejected in the flow: chunks of
concrete, sections of rebar, and, most disturbingly, what looked like
pieces of sandstone, arced high above the river. The tunnels had run
only briefly at 20,000 cfs and had been throttled back to 10,000 before
they were shut down. Since the reservoir was still below the tops of the
radial gates, the gates were shut and inspection teams descended into
the tunnels in a little cart eased down the 55 degree slopes by a cable.
The cart was named the "I Challenge U2."
"I Challenge U2", descending left spillway. Air slot is
just above cart. Photograph courtesy US Department of Interior, Bureau
of Reclamation.
Right at the curves in both tunnels the three-foot
reinforced concrete lining had been eroded away, in a stair-step
fashion, and the much softer and porous (20-25% void) Navajo sandstone
was exposed. Meanwhile, the reservoir was beginning to rise more quickly
as the steady rains and melting snows obeyed the law of gravity. The
Bureau had no choice but to reopen the spillways—and increase the flows.
The engineers decided to hold the right tunnel somewhat in reserve and
pass most of the swelling reservoir down the left tunnel. They were
already running as much water as they could through the power turbines
and the river outlet works, the former about maxed out at 28,000 cfs and
the latter limited to 15,000 due to a design deficiency in its expansion
joints. Still the reservoir surface climbed as the rains continued and
the snow fields melted. The vibration in the dam and abutments had now
become a steady shaking, accompanied by sharp jolts and rumbling sounds.
Four-foot-high wooden flashboards were then installed on the tops of the
spillway gates—to permit the reservoir to rise higher without having to
open the gates further.
By the time the left tunnel was up to 12,000 and the
right at 4,000, another "event" occurred. The smooth sweep of water at
the left tunnel outlet was replaced by a surging, boiling flow that
filled the portal. Obviously, the engineers concluded, the damage had
gotten so bad that a "hydraulic jump" had been created. The tunnel was
being converted into a pressure conduit. This was bad. Very bad. The
sweep had to be restored and the only way to do it was to increase the
flow. But the increased flow would intensify the rate of damage. Soon
the flow at the right portal lost its sweep, so its flow also had to be
raised. In the meanwhile the fronts kept coming. The National Weather
Service predicted increasing rain storms in the Upper Basin.
Shortly, the water level was so high that the gates
could no longer be shut. The flimsy flashboards would be overtopped and
quickly carried away, sending a massive, uncontrolled, and prolonged
surge from 190 miles of reservoir down each tunnel.
In a demonstration of astonishing bureaucratic
efficiency, the Bureau designed, built, and attached eight-foot steel
flashboards to the tops of the gates in just a few days. Still the
reservoir crept toward the crests of the new boards as the rains
continued without relief and the snows disappeared with the rain. By the
time the left tunnel was running at 32,000 its discharge was turning the
whole river below the dam a distinct amber color. Navajo sandstone was
being excavated from within the dam abutment like soil before a placer
miner’s hydraulic nozzle. Down in the employee dining room, located at
the base of the dam adjacent to the left abutment, a worker later said
that it sounded like the artillery barrages he had experienced in Viet
Nam. Everyone was "pretty nervous and on edge" he said.
The integrity of the dam itself was never really an issue, even for the
most timid hand-wringer in the Bureau’s engineering staff in Denver. But
what was of growing concern, and not even hinted at in public statements
both during and after the flood, was the possibility that the plunging
water, now working on the abutment at 1,000 tons per second, would erode
enough sandstone from around the diversion tunnel plug in the left
spillway that there would be a connection to the bottom of the
reservoir. There would be no way to stop the high pressure leak that
would uncontrollably grow in volume as it cut like a liquid laser
through the aeolian rock. The whole reservoir would drain. No more water
skiing. Besides the rain and snowmelt, over the course of a month or two
the entire 27 million acre feet behind the dam would be sent on its way
to the Gulf of California, in the process taking out much of the
riverside municipal development, from Laughlin to Yuma, and all the rest
of the dams down the river—except Hoover. Wedged into Black Canyon’s
concrete-like andesite breccia, Hoover is so over-designed that it could
withstand a prolonged and extreme overtopping.
All the early flood flow in 1983 was contained behind Hoover because,
unlike Powell, Mead Reservoir is required to maintain at least five
million acre feet of flood storage space. But as the flood persisted,
the Lower Basin bosses at Boulder, Nevada, were obliged to open the
spillways on their old art deco dam. Lowland flooding occurred from
below Bullhead City to beyond the Parker Strip as the discharges from
Hoover rose to over 40,000 cfs.
The total discharge from Glen Canyon peaked at 92,000 cfs and the
reservoir topped out on July 15, lapping less than a foot below the tops
of the steel flashboards and only six feet below the crest of the dam.
Inspection of the left tunnel revealed a hole carved into the sandstone
at the tunnel plug nearly 50 feet deep and 135 feet long. A ten by
fifteen foot boulder was found halfway down the tunnel beyond the hole.
The right tunnel had similar but less severe damage. One-inch rebar had
been pulled out of the concrete like bones from a cooked fish.
Once the sweat dried out of the Bureau engineers’ suit jackets, they
confidently announced that there really never had been any problem. But
later rumors and leaks were to the effect that had the series of storms
continued into the peak of the snowmelt hydrograph, given the rate of
excavation of sandstone near the plug in the left tunnel, there was a
"significant" chance that a leak from the bottom of the reservoir would
have occurred. The recognized existence of a number of joints and seams
in the left abutment, possibly opened up by the weeks of shaking, could
have helped create the leak.
July 7, 1983. Flashboards, Right Spillway; original 4
feet on right, 8 feet on left. Photograph by Tom Fridmann, courtesy US
Department of Interior, Bureau of Reclamation.
September 21, 1983. Left spillway; view upstream across
"Big Hole". Photograph by Tom Fridmann, courtesy US Department of
Interior, Bureau of Reclamation.
A year after the flood, the Bureau firmly declared that
the "cavitation" that had started the damage, that soon turned into
rapidly increasing mechanical erosion, had been dealt with. After the
damage was repaired (2,300 cubic yards of concrete), the fix consisted
of cutting an annular slot, four feet by four feet, around
three-quarters of the bore in each tunnel, located halfway down the
inclined section. The cavitation had started because there was no air in
the water. Minute vacuum bubbles downstream of bumps and ridges in the
tunnel linings had imploded, starting the cavitation that, in turn, led
to cratering. Air will now be entrained in the flow as it goes over the
slot and this will provide a "cushion" to prevent cavitation from
starting. Okay, but what if the tunnels have to run so full that much of
the air will be cut off? That cannot happen, say the keepers of the dam.
Meanwhile, the Bureau is maintaining the reservoir as
full as it can each year, keeping the cash register running with as much
back-up hydraulic head as possible. And as time goes on, we’re learning
more about how the canyon country formed: steady
erosion—"uniformitarianism"—to be sure, but an increasing number of
knowledgeable folks are saying that thousands of severe
floods—"catastrophism"—
really sped up the process.
So, the Bureau of Reclamation got away with one in 1983.
No one can know, but perhaps in near-term, non-geologic time Nature will
decide to take another crack at the plug in Her river canyon.
Steven Hannon is the author of Glen Canyon, a novel inspired
by the 1983 flood. The book contains expanded documentation, including
numerous photographs, of what happened sixteen years ago at Glen Canyon
Dam, and is available through Glen Canyon Institute. |